News

Eskom has added the final 800MW unit of Kusile power station, Unit 6, to South Africa's national grid. The development represents a milestone in Eskom's strategy to add 2.5GW of new capacity by ...
The addition of Kusile Power Station’s final generation unit comes nearly eight years after the project was supposed to be completed.
Six arrested in Kusile Power Station procurement fraud scheme.Fraudulent pump purchase cost Eskom nearly R840,000.Two suspects still at large as inv ...
Kusile’s original budget was R81 billion, and its latest estimated cost, including the economic impact of its delays, stands ...
On Sunday, Kusile Power Station’s Unit 6—the facility’s final unit—began contributing up to 800MW of electricity to South Africa’s national grid for the first time. Eskom announced that ...
As winter approaches, Eskom has got a major boost, with Kusile Power Station’s final generation unit adding 800MW to the ...
Kusile Unit 6 adds 800MW to South Africa's electricity grid.Eskom aims to add 2,500MW by March 2025.Medupi Unit 4 set to return online next month wi ...
Be among those who shape the future with knowledge. Uncover exclusive stories that captivate your mind and heart with our FREE 14-day subscription trial. Dive into a world of inspiration, learning, ...
Energy experts on Monday welcomed Eskom announcing the addition 800MW to the grid from Kusile Unit 6, saying this marked a crucial step toward dealing with load shedding, which was surprisingly ...
Eskom has added 800MW of new capacity to the national grid, which is a major blow to load shedding in South Africa.
South Africa's electricity supply remains under severe strain as the Energy Availability Factor hovers around 57. 5%. With ...