The Jansen potash project has surpassed the 50 percent construction completion mark for its first phase (JS1), BHP (ASX ... and once stage 2 is complete, Jansen is expected to supply about 10 ...
BHP) potash projects are also progressing well, with Jansen Stage 1 ahead of schedule at 52% completion, and Jansen Stage 2 in its early phase at 2% completion. For 2025, BHP expects a further 4% ...
In a milestone project for the mining industry, global mining company BHP has selected ABB to deliver, install and commission three friction hoists to its Jansen Potash Project in Canada - with one of ...
In a milestone project for the mining industry, global mining company BHP has selected ABB to deliver, install and commission three friction hoists to its Jansen Potash Project in Canada - with ...