From stripped-down tracks to brand-new infrastructure, the transformation is underway — check out what’s next for the Hoboken ...
The $31 million PATH project to rebuild the station and infrastructure at Hoboken Terminal is at the halfway mark and officials promised multiple times on Thursday that it will be done on time.
The work includes repairing 4,500 feet of tracks, as well as updating platforms, switches and train cars. The Hoboken station was flooded by Superstorm Sandy, and some of the needed improvements ...
Hoboken's PATH station will close for repairs on ... ballast (the rocks underneath that drain moisture and keep the tracks situated) and “third rail” that feeds electricity to trains, along ...
Officials held a Jan. 27 briefing to prepare the public for the upcoming closure of the Hoboken PATH ... The full station closure enables the agency to complete track and station work on an ...
Other work includes service to 4,500 feet of track between Hoboken station and the two tunnels and replacing other switches. Even the third rail that powers trains is being replaced. The concrete ...
The Hoboken PATH station will close for 25 days starting Thursday for track and station work, requiring commuters to make alternative plans for travel into New York City. The full-station closure ...
“The PATH train runs so smoothly most of ... and repairs at the Hoboken station are poised to fix 4,500 feet of track in the two tunnels leading into the station. panynj NJ Transit will ramp ...
Let the commuter headaches begin: The Hoboken PATH station is closed for 25 days starting Thursday for track and station work, requiring riders to make alternative plans for travel into New York City.