Kusile’s original budget was R81 billion, and its latest estimated cost, including the economic impact of its delays, stands ...
The Kusile Power Station, situated near Emalahleni in Mpumalanga, is now one step closer to full completion with the addition ...
The addition of Kusile Power Station’s final generation unit comes nearly eight years after the project was supposed to be ...
Kusile Power Station’s Unit 6—the facility's final unit—began contributing up to 800MW of electricity to South Africa's ...
In a statement on Monday night, Simelane reacted to a News24 report alleging that during her tenure, the company inflated ...
Concor recently showcased its engineering and construction expertise at Eskom’s Kusile power station in Mpumalanga by taking on a critical project to restore the power station’s boilers. This was in ...
Energy Minister Kgosientsho Ramokgopa presented a detailed strategy to stabilise the country’s fragile grid and drive ...
Kusile Power Station’s Unit 6 is now online, adding 800MW to South Africa’s grid. Eskom aims to boost capacity further.
Unit 6 of Eskom's Kusile Power Station has been successfully added to the national grid. Eskom announced that the final unit ...
Eskom has added the final 800MW unit of Kusile power station, Unit 6, to South Africa's national grid. The development ...